The F7 to Double Bay
The F7 ferry runs between Circular Quay and Double Bay, on Transport for NSW's timetable for the route, valid from 2 March 2026. Transport for NSW brought ferry services back to Double Bay Wharf on Thursday 21 December 2023, when the upgraded wharf opened.
The route, from Circular Quay
The timetable from Transport for NSW names the route F7 Circular Quay to Double Bay. It records that Sydney Ferries runs the services, and that a trip is paid for with an Opal card or a contactless payment. It also says every ferry and every new wharf on the network is wheelchair accessible, that some older wharves may not have the facilities a person needs, and that at low tide the ramps grow steeper and a wheelchair user may need assistance. At Circular Quay the wharf a ferry leaves from or arrives at can change at short notice, so the departure board is worth a look on the way through.
Double Bay Wharf is not the route's only wharf: Transport for NSW's community update of May 2023, issued before the closure, says the F7's other wharf would keep its timetable unchanged. Passengers heading to the bay were pointed to ferries from the Darling Point and Rose Bay wharves, to trains at Edgecliff Station and to nearby buses.
The wharf's return, 21 December 2023
The upgrade was delivered under the NSW Government's Transport Access Program, which Transport for NSW's project page describes as an effort to give New South Wales safe, modern and accessible public transport infrastructure, improving access for people with disability or limited mobility and for parents and carers with prams. Consultation on the plan ran between Monday 29 March and Wednesday 5 May 2021, and the Review of Environmental Factors for the proposal was on display for comment from Friday 15 October to Tuesday 16 November 2021.
Transport for NSW set the start of work for Tuesday 13 June 2023, with the wharf to close for around six months, weather permitting. Transport for NSW said the work would run through the cooler months to keep its effect on the local sailing club and other water users small.
Transport for NSW's May 2023 update sets out what the upgraded wharf includes: a dual-sided floating pontoon with a gangway, a covered waiting area, seating with weather protection, and improved lighting and security.
The gangway connects to a jetty, so the way from street level to a ferry stays step-free, and after feedback from the local community the design was changed to let recreational and smaller vessels berth too. All of it is meant to make the wharf easier and safer for people with additional mobility needs, for parents and carers with prams and for travellers with luggage.
Woollahra Council delivered the landside work, Transport for NSW's project page says, upgrading footpaths and bringing the accessible car parking spaces on Bay Street up to standard. The wharf design also carries stories of Country, worked in with the Gujaga Foundation, according to the nsw.gov.au media release on the opening.
Transport for NSW's December 2023 update dates the return: F7 services resumed at the wharf on Thursday 21 December 2023, with the upgrade complete and its new accessibility features in use. The media release on the opening, published on nsw.gov.au, described a more accessible and modern wharf, giving ferry users safer, step-free access from street to ferry, delivered through the Transport Access Program. The December update said the site sheds, buildings and fencing would be removed over the following days, and the grassed area reinstated and reopened to the public.
Other ways in
Edgecliff Station is the rail option Transport for NSW named for the closure, alongside the Darling Point and Rose Bay wharves and nearby bus services. The heritage impact statement Transport for NSW published for the station's upgrade puts it underground, beneath the Eastpoint Food Fair where New South Head Road meets Ocean Street, about 3 km south east of the Sydney CBD, with Sydney Trains running it on the Eastern Suburbs Line.